Kırıkkale CCGT – Time and Money Claim

Robust Expert Services Ltd provided contract and claims support on a 950MW combined cycle gas power plant project in Turkey, focused on time entitlement and associated cost recovery.

Role / scope
Support included entitlement and risk review, identification of claimable events, and strengthening of contemporaneous records for delay and cost substantiation under a bespoke EPC contract governed by English law. We reviewed the baseline and updated programmes, revised programmes, and variation submissions to confirm suitability for delay analysis and claim presentation.

 

Typical outputs

  • Entitlement/risk overview and claim strategy (events, strengths/weaknesses)

  • Delay analysis for compensable time (programme-based assessment)

  • Prolongation cost approach and average daily running cost calculations

  • Claim exhibits: event chronology, programme extracts, assumptions/constraints, and evidence register

 

Contract forms
Bespoke EPC (English law)